Seven stages, survey to flood test

How a Meridian bathroom actually gets built

Most of what goes wrong in a bathroom goes wrong before the tile is set. This is the order we work in, and what happens at each stage.

Stages
7
Survey
Free, 2 hours
Flood test
24 hours
Hands drawing a bathroom setting-out plan with a ruler and pen.
  1. Survey

    2 hours on site, no charge

    We measure the room, look at the framing and the joist direction where we can, find the existing vent route, check the water pressure and photograph everything. Most of what determines the cost of your bathroom is decided in this two hours.

    • Room measured to the millimetre, including out-of-square walls
    • Joist direction and depth checked where access allows
    • Existing exhaust route traced to its actual termination
    • Static and flowing water pressure recorded
    • Age of house noted for lead-safe and asbestos considerations
  2. Measured drawing

    5 to 8 working days

    Plan, two elevations and a tile setting-out drawing at 1:20 showing every joint line, the niche position, the valve height and where the cut course lands. You approve this before anything is ordered.

    • Plan at 1:20 with fixture clearances dimensioned
    • Two elevations minimum, four for an ensuite
    • Tile setting-out with every joint line drawn
    • Rough-in dimensions fixed: valve, head, waste, blocking
    • Written scope and a fixed price against the drawing
  3. Selections

    2 to 6 weeks, driven by lead times

    Tile, stone, grout, glass and fixtures chosen against the drawing rather than against a mood board. Every selection comes back with a lead time attached, and nothing is ordered until the whole set is confirmed.

    • Slab yard visit for any natural stone over 8 sq ft
    • Grout chosen against the actual tile sample, not a chart
    • Wet DCOF confirmed from the technical sheet for every floor tile
    • Lead times recorded and the programme built backwards from the longest
    • A single confirmed order, so nothing arrives out of sequence
  4. Strip out

    1 to 4 days

    Containment at the door, floor protection on the route in, and the room taken back to framing. This is when we find out whether the house agrees with the survey.

    • Zippered containment at the door, negative air where needed
    • Protected route from the door to the skip
    • EPA Lead-Safe practices on any pre-1978 house
    • Framing, subfloor and joist condition photographed as found
    • Any variation priced in writing before work continues
  5. Rough-in

    3 to 6 days

    Plumbing, electrical, blocking and backer board. The dimensions fixed on the drawing get built here, and everything is inspected and photographed before it is covered.

    • Valve, head, waste and supplies set to the drawing heights
    • Blocking rated to 250 lb at every bar, rail and bench position
    • Exhaust ducted in rigid metal to an exterior termination
    • Backer board with taped joints filled in thinset, never drywall compound
    • Photographed wall by wall before anything is covered
  6. Waterproofing and flood test

    3 to 5 days including cure and test

    The layer that actually keeps water in the room. Membrane applied and banded, pan pre-sloped, then twenty-four hours of standing water over the drain with a photograph at fill and at drain.

    • ANSI A118.10 liquid or sheet membrane, corners and planes banded
    • Wet-film thickness gauged and logged as a liquid membrane goes on
    • Pan pre-sloped at 1/4" per foot before the membrane, not after
    • Drain flange bedded and clamped with the weep holes kept clear
    • 24 hour flood test to one inch over the flange, photographed twice
  7. Tile, fit-out and handover

    6 to 14 days

    Tile set to the approved layout, glass templated on the finished surface, fixtures fitted and commissioned. You get a snag walk, a care sheet and the whole photographic file.

    • Tile set to the approved layout, coverage checked by pulling a tile
    • Grout to the schedule, silicone at every change of plane
    • Glass templated on finished tile and fitted a week later
    • Thermostatic valves commissioned and scald limits recorded
    • Snag walk, care sheet, warranty document and the project photo file
What is behind your tile

Six layers, and only one of them is waterproof

Cement board is a substrate, not a barrier. The layer that actually keeps water inside the room is a bonded membrane applied over it, banded at every corner, and gauged as it goes on. Here is the assembly we build in every wet zone, from the framing out.

123456room side at the top
Wall assembly, framing at the base to grout at the face. Not to scale.
  1. Framing

    2x6 studs at 16" o.c., blocking at every grab-bar and niche location

    5-1/2" (140 mm)

    We block for grab bars in every shower, whether or not one is being fitted now. Blocking costs nothing today and a torn-out wall later.

  2. Backer board

    1/2" cement or foam backer board, ANSI A118.9, screws at 8" o.c.

    1/2" (12.7 mm)

    Never gypsum board in the wet zone, including behind a tub surround. Joints are taped with alkali-resistant mesh and filled with thinset, not drywall compound.

  3. Bonded waterproof membrane

    ANSI A118.10 liquid or sheet membrane, corners and changes of plane banded

    20 to 25 mil liquid, or 0.008" sheet

    This is the layer that actually keeps water in the room. Liquid membranes are checked with a wet-film gauge as they go on, because 12 mil of a 20 mil product is not waterproof.

  4. Thinset mortar

    ANSI A118.15 improved modified thinset, notch sized to the tile

    3/32" to 1/4" after collapse

    Wet-zone coverage must reach 95%. We pull a tile at least once per wall and photograph the back of it for the file.

  5. Tile

    Porcelain, ceramic or sealed natural stone, set to the agreed pattern

    1/4" to 1/2" (6 to 12 mm)

    The visible layer, and the last thing that keeps water out rather than the first.

  6. Grout and sealant

    Grout to the joint; 100% silicone at every change of plane

    Joint width, typically 1.5 to 5 mm

    Inside corners, the tile-to-pan joint and the tile-to-tub joint are silicone, never grout. Grout is rigid and will crack where two planes move against each other.

And the floor, in order

  1. Subfloor deflection checked to L/360 for ceramic, L/720 for natural stone

  2. Pre-slope formed at 1/4" per foot (2%) to the drain before any membrane

  3. Bonded or clamped membrane, drain flange bedded and clamped with the weep holes clear

  4. 24 hour flood test to 1 inch over the flange, photographed at fill and at 24 hours

  5. Uncoupling membrane or heat mat set into thinset over the tested assembly

  6. Tile set, joints grouted, perimeter and drain joints sealed with silicone

Fixed at rough-in, free to get right, expensive to fix

Fourteen dimensions we set before the wall closes

Everything here is measured to the finished surface, not the stud. Half an inch of backer board and tile moves a toilet flange out of code.

  • Toilet flange, centre

    12" (305 mm)

    from finished back wall

    IRC. 10" and 14" rough-ins exist on older Denver stock.

    Measure to the finished wall, not the stud. Half an inch of backer and tile moves the bowl.

  • Toilet side clearance

    15" minimum (381 mm)

    from centre of bowl to any wall or fixture

    IRC P2705.1

    We design to 16" or 18" where the room allows. 15" is legal, not comfortable.

  • Toilet front clearance

    21" minimum (533 mm)

    from front of bowl to the nearest obstruction

    IRC P2705.1

    Check this against a swinging shower door and a vanity drawer at the same time.

  • Shower valve height

    45" to 48" (1,145 to 1,220 mm)

    from finished shower floor

    Manufacturer spec

    Lower for a tub/shower (28" to 32"). We set it where the client actually reaches.

  • Shower head height

    76" to 84" (1,930 to 2,135 mm)

    from finished shower floor

    Manufacturer spec

    Set to the tallest regular user plus 3 inches. Rain heads go higher, to the ceiling drop.

  • Handheld slide bar

    48" to 72" range (1,220 to 1,830 mm)

    from finished shower floor

    Manufacturer spec

    Needs blocking behind the board across its whole length, not just at the fixings.

  • Vanity top height

    32" to 36" (815 to 915 mm)

    from finished floor

    Convention; 34" is the accessible maximum

    36" comfort height suits most adults. 32" suits a shared family bathroom.

  • Vanity drain rough-in

    18" to 20" (455 to 510 mm)

    from finished floor, centred on the bowl

    Manufacturer spec

    Offset the drain to the back wall for drawer-front vanities, or the top drawer will not close.

  • Mirror bottom edge

    4" to 6" above the backsplash

    from vanity top

    Convention

    Leave room for the faucet to swing and for a soap pump to stand.

  • Wall sconce centre

    60" to 66" (1,525 to 1,675 mm)

    from finished floor

    Convention; at or just above eye level

    Paired sconces at eye level light a face from both sides. An overhead fixture alone will not.

  • Grab bar, horizontal

    33" to 36" (840 to 915 mm)

    from finished shower or tub floor

    ICC A117.1

    Needs solid blocking rated to 250 lb. We block at rough-in in every shower we build.

  • Shower bench height

    17" to 19" (430 to 480 mm)

    from finished shower floor

    ICC A117.1

    Depth 15" minimum. Slope the top 1/4" per foot to the drain so it sheds water.

  • Niche, shower

    48" to 54" centre (1,220 to 1,375 mm)

    from finished shower floor

    Convention; set between studs

    Sill sloped 5 degrees out. A flat niche sill holds water and stains the grout first.

  • Curbless entry, recess

    1-1/2" to 2" (38 to 50 mm) joist recess

    from top of subfloor

    Depends on joist depth and direction

    Only possible where joists run the right way and can take a sistered header. We confirm on the survey, never on the phone.

Start at stage one

A survey is two hours and costs nothing. You get the structural answers before anybody discusses tile.